We manage multiple live projects with clear milestones and daily progress updates. Below is a snapshot of current works, percent complete and next milestones.
Each project is tracked with weekly sprints and on-site quality checks to keep schedules tight and predictable.
Jubilee Hills — 3BHK Villa
Structural & Finishes
- Foundation: Completed ✅
- Superstructure: Completed ✅
- MEP & Finishes: In progress — expected 6 weeks
Next check: Roof waterproofing sign-off (this week)
KPHB — Minimal Duplex
Turnkey Interiors
- Frames & Roofing: Completed ✅
- Plumbing: In progress
- Interiors: Starting next sprint
Next check: Plumbing pressure test (2 days)
Gokul Plots — Corner Villa
Exterior & Landscaping
- Exterior Plaster: Completed ✅
- Windows & Doors: Completed ✅
- Landscaping: Finishing
Next check: Landscaping final walkthrough (5 days)
Westend — Luxury Townhome
MEP & Handover
- Excavation: Completed ✅
- Foundation: In progress
- Structure: Next sprint
Next check: Foundation concrete pour (3 days)